Abstract
One of the most irradiated Spallation Neutron Source (SNS) accelerator components is ring injection dump (RID), which is located downstream of the accumulator ring injection section. The unstripped and only partially stripped H- beam is discarded in the injection into the accumulator ring and is redirected to the RID, which is about 5% of the full beam current. According to the accelerator operation plan, the beam stop and the window assemblies of the existing RID will be removed and replaced, when they have reached their end-of-life. This procedure, which includes multiple steps, is scheduled to take place during facility maintenance period in January 2023.
In order to support job planning and meet ALARA requirements during removal and exchange of the components, dose rates for each stage of exchange operation are calculated.