|
|  |
|
SPI Readiness Reviews
[SPI Readiness Review Program] [FY 2003-2010 Reviews] [Where are the greatest risks (cables)?]
[HV issues on present projects] [2011 Plans] [Nitrogen Dielectric Database]
FY 2011 Plans
- Readiness Reviews:
- Plan a 4th round of readiness reviews in 2011 of each FCL project as they complete detailed design, fabrication and begin off-grid and on-grid testing
- Conceptual design review for the fault current limiting, superconducting transformer project is planned in early 2011.
- “Lessons-learned” reviews are planned as these projects finish their in-grid demonstration periods.
- In 2011 the web-site will be upgraded further
- Lessons-learned from prior projects
- General design guidance on high voltage, vacuum, etc.

|
|
 |